Restoration and Renewal of the Palace of Westminster

Recorded Commons debate sitting on Wednesday, 25 November 2026: 41 speech excerpts from 41 speakers in our Hansard import. This is a recorded speech sitting, not a claim about the House timetable. Source: Hansard. Excerpts below are not the full transcript — read the full debate on Hansard.

I beg to move, That this House expresses grave concern at the enormous projected costs of the Restoration and Renewal Programme, estimated at between £11.1 billion and £39.2 billion; believes that the scale of expenditure contemplated is particularly difficult to justify given the severe pressure on public finances; recognises the urgent need to address serious deficiencies in the Palace of Westminster’s fabric, infrastructure and fire safety, while expressing concern at the absence of an agreed budget or affordable scope of works to do so and the continuing failure to establish effective governance, financial control and accountability; and questions the assumptions underlying the proposals for the extensive decant of Parliament, the resulting disruption to parliamentary proceedings and the substantial additional costs involved. This, as the House will be aware, is nominally an Opposition day debate. However, the motion stands first in my name, and, on the Opposition Benches, it is subject to a free vote. It is, it must be said, a rather unusual procedure, but we have been forced to it by the Government’s unwillingness to act over the past nine months on the restoration and renewal of the Palace of Westminster. The R and R client board published its costed proposals document on 5 February. Since then, the Government, who control the business of the House, have done nothing about it. That is nine whole months. You will be pleased to know, Madam Deputy Speaker, that I have just seen that we have been successful: the Government have at last published their motion, just a few minutes ago. I am delighted by that fact. [Interruption.] The Leader of the House, who is grumbling somewhat from a sedentary position, may try to decry this debate as an attempt to make this piece of House business party political—[Interruption.] Thank you. He may criticise our call to do the necessary work at a far lower cost as a needless further delay, but the opposite is true. My colleagues c

I inform the House that Mr Speaker has selected the amendment in the name of the Prime Minister. I call the shadow Leader of the House.

I remember debating this when I was in the House in 2017—obviously there were a number of Conservative Governments in that subsequent period who did not bring forward a resolution. The right hon. Gentleman’s motion sets out the things he disagrees with and what he thinks the cost will be. At what point will he publish his alternative measure so that if we do support this motion today, we know what we are likely to back?

I have been an advocate of the “kicking the can down the road” strategy, because this proposal has not made sense financially and it is still not proven. However, as the motion says, the Opposition also accept that the situation is not sustainable. It is quite clear that all this motion is asking for is further analysis. We have heard that from the hon. Member for Boston and Skegness (Richard Tice) and from the Opposition Front Bench. There is no risk in taking a few more weeks before the Leader of the House’s motion is put in front of Parliament, so as to have as much consensus building as possible, because the challenges are quite legitimate.

Since the beginning of this week I now sit on the House of Commons Commission, which, together with the House of Lords Commission, makes up the client board for this programme—there has been some quick reading and quick learning! I thank the Opposition for tabling this motion. I say that with some affection, because it is not every day that a party turns up to complain about its own homework. Nobody in this House should be relaxed about spending tens of billions of pounds of public money, and the Liberal Democrats share that concern. But let us remind the House whose idea this was. A Conservative Leader of the House, Dame Andrea Leadsom, tabled the motions in 2018 that sent this House on its way out of the Palace. A Conservative Government introduced and passed the Parliamentary Buildings (Restoration and Renewal) Act 2019, and when Notre-Dame burned down that year, a Conservative Leader of the House told us all to “get on with it”. Now, a Conservative Opposition table a motion expressing “grave concern.” Grave concern about what exactly—their own signature?

The grave concern is the truly eye-watering sums that are being debated. My constituents, and I suspect those of the hon. Gentleman, will be appalled that we should be spending that sort of money on ourselves—and that is how it will be presented, rightly or wrong. Does he not share those concerns?

I rise to speak in favour of the Government’s amendment. I support a restoration and renewal programme that happens at the right pace, and that ensures good value for money. Dame Andrea Leadsom, the former Conservative Leader of the House, when introducing the R and R programme in 2018, said: “We do need to get on and take a decision”.—[Official Report, 31 January 2018; Vol. 635, c. 887.] I agreed with her then, and I still agree with her. It is up to us to move this forward. We are the custodians of this brilliant place. Now is the time to invest in, and improve, our democratic home. It will take more time than we want, because it is such a vast estate with so many aspects to protect. It will cost more money than we want to spend, but the fine stone, the beautiful windows, the great works of art and, of course, this wonderful Chamber all need to be properly looked after. In the end, I believe the effort will be worth it, but we must help bring the works in at a good price. There are other benefits; our economy will receive a much-needed boost from skilled people across our country carrying out these necessary works. Many parts of our country will benefit, whether it is the slate coming from Wales or the textiles coming from the west midlands. If we do not move forward with the restoration and renewal programme now, there will be serious consequences. We face critical risks, including fire, asbestos and falling masonry. Anybody who has been down to the basement of the Palace and seen the archaic muddle of pipes and wiring there will understand what I mean. While the Palace is a UNESCO world heritage site and the Elizabeth Tower is a global icon, most of all, the people of this country know that it is this Chamber—where we raise and work through the difficult challenges facing our world—that we must protect. That is why this place is worth investing in, and why it is priceless. It is our duty to invest in it, and when the work is done, we should return to this democr

I first got involved in this issue over 10 years ago. Our colleague Jacob Rees-Mogg, who has been mentioned, served on the original Committee that 10 years ago recommended a full decant to Richmond House. It did not fill us with great enthusiasm that that Committee got its measurements wrong—the IKEA-style chamber could not fit into that part of Richmond House, and of course there would have been enormous expense. I have been working on this issue all this time, and it was apparent to me 10 years ago that we were constantly proposing gold-plating and decanting instead of getting on with the work. The delivery authority—all this period, and certainly from 2019—has been spending vast amounts of taxpayers’ money endlessly developing plans and not repairing the building. It has proposed endless gold-plating works, and it has devised completely unnecessary new ideas, such as a new underground visitors’ entrance. I agree that it is very hard to make things happen in politics, but if you are relentless, you can stop things from happening. I know that I have been a deep disappointment to the right hon. Member for Alyn and Deeside (Sir Mark Tami).

Madam Deputy Speaker, “Without action, at best the Palace will be in a process of managed decline. At worst, a catastrophic event could occur that endangers lives and interrupts the functioning of democracy in the UK…A failure to act would have serious consequences for taxpayers and future generations.” These are not my words, but those of the Public Accounts Committee—which is chaired by the hon. Member for North Cotswolds (Sir Geoffrey Clifton-Brown), who is not here today—in its report, “Restoration and Renewal of Parliament: Costing and governance”, and the devil is in the detail. That is a fair assessment by a cross-party group of 16 MPs. The Committee set out a number of conclusions and recommendations. There were eight in total, including engagement with parliamentarians, a timetable of work from the client team, and the question of a “competitive dialogue” procurement approach in relation to gaining clarity on the scope and the cost band schedule. In addition, the Committee set out the remaining cost estimates for phase 1 and suggested a detailed delivery schedule. The Committee also recommended the production of an integrated plan across a number of themes and a temporary accommodation proposal, as well as setting out the risks associated with divided responsibilities. Then there was the recommendation about the simplification of the phase 1 governance process, which will be reviewed ahead of the start of phase 2. That covers a number of the issues that Members have raised today. The final two recommendations relate to a potential restoration and renewal Select Committee, based on the Canadian model—I make no comment about that, but the Public Accounts Committee put that in its recommendations—and to an annual update on the programme’s progress, with an independent annual examination of the programme. Those recommendations are set out in the context of a full decant of both Houses, which would cost £11.1 billion to £15.6 billion over the best part of two de

I declare an interest as co-chair of the disability parliamentary Labour party group and chair of the cross-party Members’ accessibility group. I rise to speak against the Opposition motion, and to support the points in the Government’s motion that Parliament is an important heritage asset and a large employer and that delay in making the necessary changes will lead to soaring costs for the British public. I make this case in support of the Government on the basis of 20 years working in disability law and policy, and over two decades driving access audits, physical adaptations and infrastructure improvements to public buildings from university institutions to civic town halls. Consequently, I firmly disagree with the Opposition that the scale of changes to Parliament as part of restoration and renewal are particularly difficult to justify. Indeed, I think the reverse. It is a great travesty that the Conservatives spent 14 years failing to implement the Equality Act 2010 in the fabric of the building that makes the laws of our country, thus driving up the cost of restoration and renewal through their dither and delay. Making this case is especially important as we are in the middle of Disability History Month, the theme of which is “Disability, Politics and Democracy”. The accessibility of our democratic institution increases the inclusion in our politics of disabled people. When I was growing up in my constituency and deciding what I wanted to do for my degree, I understood then, as I do now, that law is power. Just as we need our courts to include representation of a wide range of protected characteristics, so too do we need to ensure that this House has the widest possible representation as the place of our nations’ legislators. I am proud to be the first ever Member of Parliament with a congenital limb difference. Disabled people make up 20% of the voting-age population in the UK, yet at the last count only eight of the 650 of us elected to this Chamber have a di

Does my hon. Friend not find it incredible that 88% of this building is not wheelchair-accessible? In the case of a fire, what would happen to people who were here in wheelchairs? Again, that is not gold-plating.

Specifically on that point, I was at an event in the Churchill Room and there was a young man in a wheelchair. I decided to accompany him out of the building and it was quite an assault course to get out. I wholeheartedly agree with my hon. Friend. She is making a powerful and important speech. We need to put in investment in order to enable disabled people. They are disabled by institutions such as this House, unfortunately, and those elsewhere in the country. We need to end that and to enable them.

I want to put on record my thanks to all the House officials who, over the last 10 years, have had the deeply unenviable task of trying to come up with recommendations, solutions, ideas and briefings for MPs of this Parliament and previous ones. It has not been easy for them. I agree with the Leader of the House that far too many confusing signals have been sent to House staff about what this House and the other place want. I have always argued, since I first became the MP for South Leicestershire over 10 years ago, that this building is large enough to zone off, repair and get on with it, as the Father of the House, my right hon. Friend the Member for Gainsborough (Sir Edward Leigh), has rightly reminded colleagues. We sit in a Chamber that many, even some MPs, think is a Victorian Chamber, but of course it is a 1951 edifice. In May 1941, the Luftwaffe struck a direct hit on what was the Victorian Chamber, blowing it to smithereens. We have passed the portrait of Winston Churchill on the back stairs at the north end hundreds of times, in which he is standing in the ruins of the Victorian Chamber. Within the space of weeks, the House of Commons was relocated to the House of Lords, and the House of Lords was relocated to the Robing Room. Notwithstanding all the Victorian pipework, the asbestos and all the other infrastructure and plant that continues to work to this day, they seemingly managed to do it. People often say, “Oh, but the health and safety laws were different back then.” Yes, they were, but not so different that people were unable to work around the building and construction work. What other buildings have commonalities with this Chamber? The Chair of the Administration Committee, the hon. Member for Blaenau Gwent and Rhymney (Nick Smith), rightly referred to Notre-Dame, but I encourage him, and indeed the whole Committee, to visit the University of Glasgow. That is another Gothic revival edifice, and it is about a quarter of the size of this building. In

In around 2009, I hand-delivered a pre-qualification questionnaire to Parliament as the company I was working for at the time wanted to be a part of that bonanza. Many years later, as the hon. Gentleman’s colleagues are talking about these huge contingency plans, does he not recognise that the delay has made many contractors not want to work with us, and that they will probably be building a hell of a lot of risk into what they put in their estimates?

Green MPs think the motion is incredibly irresponsible, and I have heard some unusual and, quite honestly, dangerous suggestions from people who, with respect, I suspect have never picked up a screwdriver, yet who are apparently now experts in construction. Does the hon. Gentleman agree that we need more people from ordinary backgrounds and with those skills in this place? When I was working as a plumber, there is no way I would have advised a customer to keep spending eye-watering sums of money rather than just getting on with the job. We need to make these Benches more accessible for everyone.

I disagree with some of the things that the hon. Member for York Outer (Mr Charters) just said, but I agree vehemently with his points about heritage skills. I will not repeat his points, but I agree with them completely. It is clear that there is broad agreement across the House that the Palace of Westminster must be restored. The question before us is not whether that work should take place, but how we deliver it in a way that protects a historic building while providing value for money for the British taxpayer. As a former Heritage Minister, I have a particular passion for protecting our historic built environment. Parliament is one of the most recognised symbols of our democracy. It is a UNESCO world heritage site and a building entrusted to us by previous generations to be preserved for those who come after us. For centuries, it has been at the heart of our national life, witnessing some of the most significant moments in British history. It is precisely because this institution matters so much that we must get its restoration right. It is therefore worrying that no one appears to be truly in charge. Cost estimates continue to rise and timelines continue to slip, yet accountability remains fragmented across committees, boards and delivery bodies—I think we have had five boards and counting. If everyone is responsible, we know that no one is responsible, so governance is key. Especially at a time when we are asking families to make difficult financial decisions, Parliament cannot except itself from the standards that it expects of every Department and every household budget. Every pound spent here is a pound that cannot be spent elsewhere. We must therefore ensure that the process is streamlined wherever possible, that unnecessary costs are eliminated and that savings are secured without compromising safety. The Notre-Dame restoration has been commented on several times already today. It cannot be directly referenced—it is not directly the same thing—but there a

For the record, I have consistently voted for a full decant, because I believe we need to sort this out and grip it. Would my hon. Friend agree with me that the test is not just whether we can get the maintenance right, but whether we, as custodians of this building, can work as a Parliament with clear governance and clear direction, not changing our mind and scoring points, and get this part right? I fear at the moment that the public will see what has gone on and worry that we are going to kick this down the road, spending money and wasting money. We need to get it right once, properly—not by designing the most expensive building in the world, but by making it safe and workable for the next generation.

I thank the Leader of the House for being so generous in giving way. Last year, along with probably most of the MPs in the Chamber, I went on an R and R tour of Parliament. At that time, we were presented with three choices, and there was a middle ground, which to me seemed extremely sensible. I have yet to hear a good answer as to why that middle ground has been removed from the final options. We are being given a binary choice between something that is incredibly expensive and—well, actually both are incredibly expensive.

As a member of the Public Accounts Committee, which has scrutinised the proposals in some detail, along with many other historical infrastructure projects, I am surprised that the right hon. Gentleman and his party seem to be ignoring the Committee’s recommendations that Members now have plenty of information to make a decision and that it is vital that we get on and start with this project as soon as possible.

In this debate, we have heard many wise words from Conservative Members. It is just a shame that they did not voice those wise words when they were in power. The decision to decant and get on with the works was taken on 31 January 2018. A similar resolution was passed in the House of Lords. I and other Members who were in Parliament then voted; it was a cross-party vote, not a whipped vote, because it was a matter for the House. In that debate, the then Leader of the House, Dame Andrea Leadsom, spoke about the urgent need for restoration and renewal works to begin because of, among other things, the “hotch-potch of pipework and wiring”—[Official Report, 31 January 2018; Vol. 635, c. 880.] in the basement of the Palace, the risk of fire and the need for asbestos removal. A number of Members who are on the Opposition Benches today took part in that Division and voted in the way they wanted to vote. At the time, the cost of doing the works was around £3.5 billion. Since then, there has been a 36% increase in the consumer price index—that is inflation alone. Dame Andrea Leadsom said at the time that the debate we were having, on 31 January 2018, should have taken place 40 years earlier. Following the two votes that we had, in the Commons and in the other place, an Act was passed: the Parliamentary Buildings (Restoration and Renewal) Act, which set up a Sponsor Body to get on with the works. Unfortunately, the Sponsor Body did not do its job, and its powers were then subsumed back into Parliament. The restoration works have a chequered past, and it is incumbent on all of us to make sure that we start those works as soon as possible, progress them and get things done. Other Parliaments seem able to do this: Canada has decanted its Parliament, which is still undergoing restoration and renewal works; the Dutch Parliament has been decanted, and works are under way; the Austrian Parliament has already done its works. The Public Accounts Committee’s report on the cost of these

This place is not merely a place in which we live or represent others; it is the physical manifestation of what makes this country great—indeed, the greatest country that has ever been. This place is where we expanded voice, and it is where different people were represented in the making of powerful decisions that not only ensured they had political representation, which they did, but set the stage for the industrial revolution, and therefore the greatest expansion in human dignity and welfare there has ever been. We also know that in this place—in this building—we must not only preserve the values that we hold dear for future generations, but ensure that the building physically remains. As we all accept on both sides of the House, the building is not physically where it needs to be. When I say this place is a physical manifestation of what makes this country great, I refer to the fact that it was first built by one of the sons of William I, and it was where we saw the Earl of Leicester call his first Parliament in Westminster. It is where we then saw a king who tried to implement his absolutist monarchy be not only rejected by MPs, but sadly sentenced to death. It is where we saw the passage of reform Acts that ensured the representation of people and their voices in the making of decisions. This place does not just represent those events; it is where they happened. This place—and this country— was the first on Earth to see sustained economic growth, precisely because of the ways in which power spread from this area and ensured that policy was made in the interests of people outside a very narrow and select few. We also know that this place is falling apart. We know about the fire risks, and we know about the risks to the electrics and the leaks, because we see and experience them. We also know about falling masonry. I heard of one colleague who had some masonry fall on their staff member’s desk. Of course, had it fallen somewhere different, that may have had a rat

I should like to report that in the summer, the second floor of 53 Parliament Street had a complete failure of air conditioning and my staff were overheated, working illegally. There is now a complete failure of central heating, so my staff are completely freezing. I echo what my right hon. Friend the Member for Hayes and Harlington (John McDonnell) says about the conditions for our workers.

I thank the shadow Leader of the House for opening this debate and Members from across the House for their thoughtful and considered contributions. We have heard almost 20 speeches. The restoration and renewal of this place—the home of British democracy, the mother of Parliaments—was never going to be easy.

Members need to take into account the fact that this is a workplace. There are 3,000 workers who work here. They have had to endure asbestos. Some have to have their health monitored for the rest of their life. There have been floods, electrical faults and, to be frank, working conditions that are just unacceptable in the 21st century. We have a responsibility to those workers, and every single trade union representing them has made it clear that they do not wish any further delay in the refurbishment and restoration of this building.

I wonder whether the right hon. Gentleman would like to check his figures. He just said that Notre-Dame has a quarter of the footprint of the Palace of Westminster. I believe Notre-Dame to have a floorspace of 5% of the Palace of Westminster, making it one twentieth of the size. Would he like to correct the record?

Given the fact that the motion before us is unnecessarily confused, jams together different options and does not lay things out clearly, any confusion that our constituents may have today is actually because of the Opposition making them confused and angry about potential spending that is significantly above the range that we should, in reality, be discussing. Does my hon. Friend agree?

Given that the Opposition have, peculiarly, chosen this issue for an Opposition-day debate, I will start with the Conservative party. I thought its raison d’être was to conserve, but apparently not when it comes to conserving this place, the UK Parliament. The Leader of the Opposition called it akin to bankrolling billions to create a “net-zero Dubai hotel”, mocking efforts to restore this very place. I have been with the Public Accounts Committee to Buckingham Palace to see how the decisions that gripped the timeline and project management led to a successful restoration programme there. I have been underneath this building, metres below, and I thank the R and R team who do a wonderful job in explaining why Parliament needs restoring. This issue was ducked by the Conservative party for years and years. In 2018, the Labour party backed a timely decant to allow essential restoration. Who voted against that? The Leader of the Opposition. Now, more than five years after that, Conservative Members come crowing about the cost of their own decision. This is just a wider problem of a failure to deliver infrastructure projects such as High Speed 2. We saw that with Crossrail, the completion of which was delayed, and even with a garden bridge. Now Conservative Members come here pointing the finger at everyone but themselves. I have heard many contributions from Conservative Members, but what has not been mentioned? An apology. Conservative Members have a pattern: destroy public services, let large projects spiral in cost, get obliterated in a general election, and never show even a modicum of humility. They really have learned nothing. I am the son of a surveyor and joiner, and a fire safety officer—my mum. The safety of buildings is perhaps in my DNA, which is why I believe that the safety of the staff who work here—the Doorkeepers, cleaners, cooks and so on—should be central to our decision. I encourage hon. Members to go to the ticket office in Central Lobby, where a plaq

As a former Government accommodation Whip, I absolutely accept that we have to do something about the fire risk to the Palace. The hon. Gentleman has said that we should try to proceed by consensus, and I think everyone agrees that whatever we do, we must do something about that. However, does he accept that whether it is £10 billion or £40 billion for the overall solution, at a time when people’s gas prices are about to go up and they are feeling the cost of living challenge, the problem is that we would be perceived—rightly or wrongly—as spending that money on ourselves? That is the fundamental nub of the problem.

My hon. Friend is making a powerful speech. Would she describe the measures she is outlining as gold-plating?

My hon. Friend is making a very good point. Does he recognise that the independent advice and assurance panel itself recommended the scale of works proposed by the restoration and renewal programme, that the R and R client board’s assessment at the end of last year checked and benchmarked the proposals against comparable projects, including Manchester town hall, and that delivery costs per square metre are similar to those for the Canadian Parliament when judged by volume?

I assume that the hon. Member will get further into the detail of the length of time that this work will take. We are focusing quite significantly on the cost, but ultimately this will potentially mean decades of time in which our constituents will not be able to access this mother of all democracies—the Palace of Westminster. Is it the position of the Liberal Democrats that the public should be kept out of here for a significantly long period of time? Do they not want to minimise the distress caused to them?

Isn’t the problem that nobody can justify spending somewhere between £10 billion and £40 billion on repairing this great place? The issue is that the brief is wrong, because there is not one, not two, not three but four boards of governance. That is one of the first problems.

I beg to move an amendment, to leave out from “House” to the end of the Question and add: “recognises that it has a responsibility to repair, secure and protect the Palace of Westminster, part of a UNESCO World Heritage Site of global historic and symbolic significance, for future generations; notes the previous Government’s failure to support Parliament in implementing a credible Restoration and Renewal Programme in 14 years; further notes that this indecision has added significant costs to the remediation required and that further delay would only increase costs and risk catastrophic failure of the buildings, putting the safety of those who work on and visit the parliamentary estate at risk; also notes the National Audit Office Report, Restoration and Renewal of the Palace of Westminster: 2026 Update, HC 32, and the 19th Report of the Committee of Public Accounts, Restoration and Renewal of Parliament: Costing and governance, HC 90, which recommended proceeding immediately with works; notes that the Restoration and Renewal Programme will support thousands of jobs across the country; further notes that the phase one works will deliver value for money for the taxpayer by capping initial costs; and supports the Government’s commitment to table a motion for debate so that individual hon. Members can take a decision in a proper and informed way before the end of the year.” It is entirely a matter for the Opposition what they choose to debate on their Opposition day, but I have to say that their choice today is both disappointing and, frankly, odd. It is disappointing because the Opposition knew full well that the Government intended to provide time for a debate on restoration and renewal before Christmas. The shadow Leader of the House had seen a draft motion.

One thing I think we need to get clear is what is the primary purpose of this restoration. Is it fundamentally just to make the building safe or is it to try and in some way transform the building? According to the National Audit Office’s June 2026 update report, it is the former. It says: “The Palace requires extensive restoration to address serious risks and priority improvements, including deteriorating mechanical and electrical systems, fire safety issues, the presence of asbestos and the condition of the historic fabric.” Why should it take £40 billion just to do repairs?

The restoration and renewal programme is best characterised as one clouded in denial. We can see that from the costs that have already been cited in this debate. Understandably, the hon. Member for Boston and Skegness (Richard Tice) quoted from the National Audit Office report. Figure 1, on page 20, sets out the cost of decant: £11.1 billion to £15.6 billion. Those NAO costs came from the fully costed proposals from the delivery authority, but Members are kidding themselves if they think that they are the true costs. The intervention from the hon. Member for Bury St Edmunds and Stowmarket (Dr Prinsley) was a good illustration of that point. He said that we need to get on with restoration and renewal because of the work in his office on Parliament Street. That is outside the scope; it is actually covered by a different programme. It is £5.3 billion that is being spent and kept off the books. It is off the restoration and renewal books, but £3 billion of it is presented as essential to enable decant to happen. It is presented as integral to the R and R programme, but it is kept off the books. Of that £5.3 billion, a further £1.7 billion is actually work on the Palace: bridging work over the next 10 to 15 years, much of which will be ripped out because of the delay. This is work that we are going to commit to but then remove, none of which is on the restoration and renewal books.

The Leader of the House talks a lot about our democratic duty, but he fails to mention our duty as legislators and parliamentarians to take account of the public purse. Does he agree that, at the end of the day, it is taxpayers’ money that he seeks to spend?