Q Both of your organisations and many others have highlighted how the UK is not great at delivering infrastructure quickly and efficiently. Do you believe that the Bill in its current form has the potential to accelerate the delivery of major road projects? Ben Hopkinson: I completely agree that the UK has a long historical challenge with delivering infrastructure cheaply and quickly. HS2 is the most expensive railway ever built, and the Bakerloo line extension will be one of the most expensive underground lines ever built. Tramlines are double the cost here compared to other European countries. We have the most expensive nuclear power plant ever built. There is a real long-term failure to build infrastructure quickly and cheaply. On the Bill, it is good that we are getting private financing in, and that will help ease some of the burden on the state, when we are already pushed up against our fiscal limits. As I have mentioned, I have a little concern about the incentive structure, especially insofar as the private constructor has incentives to escalate costs as much as they can get away with under the ORR. A concession model might work a little better. Sam Dumitriu: One of the important things when it comes to infrastructure delivery is ensuring you have a pipeline of projects, you know what you will build next and you can plan appropriately. We have many reasons why, in the UK, those pipelines get knocked about. Sometimes you have a road that you want to build, and everyone wants it built, but someone has brought a lawsuit against the road and it is delayed by a year. That makes planning for that really challenging. One of the other problems is that sometimes those delays mean that you get pushed into different funding windows—the Treasury can reopen conversations about value for money, especially when in every Budget someone is trying to squeeze things into the fiscal rules and moving things from one period into another period, and cost-saving measures that are r
Highways (Financing) Bill (Second sitting)
Recorded Commons debate sitting on Thursday, 29 October 2026: 9 speech excerpts from 9 speakers in our Hansard import. This is a recorded speech sitting, not a claim about the House timetable. Source: Hansard. Excerpts below are not the full transcript — read the full debate on Hansard.
Q Under the French model which you have cited as a template, 91% of roads are owned by privatised companies, and that is very different to the UK. They are extremely controversial and many accuse companies in France of price gouging. We have concerns about asset management and the valuations. You have said that the RAB model is potentially ideal, but is there any element of it that you can say is better than the French concessionary model? What teeth would you give the regulator to make it so, if we were to go down that route? What is missing from the RAB model that would make it more effective? Ben Hopkinson: It is a good question. First, in the French example, I am well aware that it is quite expensive to drive on a French motorway. On the other hand, they have many more miles of motorway, and if it is too expensive you can take the equivalent of an A road for certain journeys. Judging by the number of people who drive on French motorways, I think people are generally willing to accept the costs, especially given that they have built many more miles of motorway just this century than we have in total. I could be proved wrong if it works really well, but the main challenge with the RAB model is the sheer uncertainty of whether the ORR is up to the task and has the right staff in place. It has never done this before. I know there have already been some concerns about capacity issues and general commercial experience within the ORR. I would be concerned if the private sector had large commercial control and contract teams and the public sector did not have them and was out-negotiated. That is certainly possible if civil servants are not able to properly push back on price increases. I think the fundamental incentives in a RAB model are not right for delivering one-of-a-kind, unique pieces of infrastructure. It works a lot better for infrastructure that has very clear unit costs—for example, the cost of laying 100 metres of pipe. That is good because a regulator is cl
Q I will build on some of what the shadow Minister, my hon. Friend the Member for Mid Buckinghamshire, said about tipping points. My question is to both of you, so please feel free to answer in whichever order you prefer. The shadow Minister was referring to things such as fuel duty, I am acutely conscious that the cost base of the lower Thames crossing project is going up and is as yet unknown, and we do not know what the toll will be. In a situation such as we have at the moment, where diesel is at £2 a litre and the sustainable version another 50p on top of that, costs are going right up not only for the build, but for the corporate budgets of the haulage companies and for everyday individuals, who have to manage their household budgets. If the cost goes up to a level beyond the right balance of pricing that is commercially viable for the operator, or absorbable for the family or the business, what happens? At the moment, I am worried about a white elephant across the Thames. In such circumstances, in the end all the costs would get absorbed by the taxpayer and this model goes up in smoke. I am keen to hear from you how concerned I should be about that and what alternative models there are elsewhere. Ben Hopkinson: The ultimate backstop is the Exchequer. Already the Exchequer has had to bear the cost of bringing the lower Thames crossing through planning. I think it is expected to spend about £3.1 billion on the lower Thames crossing even before private investment is brought in. If we have a circumstance where the toll is not paying back what is necessary and the private body that has financed the road falls into difficulty, the Bill states that the Exchequer is able to top up or provide payments, guarantees or low-cost loans. The backstop is therefore ultimately the taxpayer, combined with higher charges for motorists on the road.
Q It has been really clear today that cost control is a crucial element in the success of this project. Should there be safeguards for motorists within the regulatory framework where, for example, unexpected charges arise or costs are excessive? Will Godfrey: At the heart of the regulator’s responsibilities would be furthering the interests of current and future users. Those are exactly the kind of considerations that would be at the heart of how you approach the regulation, how you set up the instruments—I am referring specifically to the licence—and how you then hold the company to account against that licence. For the first control period, in the case of the lower Thames crossing, the licence would be awarded by the Department, so the particular tolling structure and the level of tolls would be set through that competition for the first licence. Thereafter, the way that the ORR operates is that the code that the ORR would be responsible for creating on the approach to tolling arrangements will clearly be important once you are past that first point. My feeling is that the arrangements necessary to provide protections to end users around, for example, tolling and toll shocks and so on feel about right to me in the enabling legislation. What is really important is what goes into the licence and what we put into the code, and then how the company responds. I hope there will be a virtuous circle, in which there is a clear signal of what is expected, we hold the company to account, it delivers and implements it, and we then take the feedback from the market. I do not know if you were anticipating a different concern, but I will pause there in case I have not answered your question.
Q Matt, I think you have already answered my first couple of questions: the legal requirement on climate was set in 2022 in the original direct consent order, and the requirement to use alternative fuels to diesel is not a significant cost driver in a scheme of this scale. However, reflecting on a conversation that you and I have had previously, I was wondering about the cost impact, and the impact on the project generally, of delays caused by uncertainty of finance. Would a Bill like this enable future schemes to have certainty of financing arrangements, and therefore get on site and be delivered more quickly? Is that a fair assumption? Matt Palmer: I think all of us recognise that annualised costs on major projects, especially mega-projects, are very difficult to deal with. They drive perverse cost behaviours, where you are trying to fit into a 12-month window, and the Government are currently moving, with the mega-projects piece, towards more of an envelope-type conversation. This is just another extension of that. You end up with a cost envelope that you are working within, with a driven timeframe that you have to deliver to, which then allows the flexibility to execute at the right time—depending on the weather and so on. It is that flex that you need in order to execute efficiently. If you are constraining yourself on cost to a budget every year, which is common, it does drive cost. This model gives you the flex that allows you to drive an efficient construction project.
Q We heard from an earlier panel that the operator has limited incentives for cost control and that there is a risk of taking “costs off the book without any level of scrutiny.” Do you understand what they are talking about in that? Will Godfrey: I think “without any level of scrutiny” is something I would take issue with, certainly as I would see the arrangements working. We have had good discussions with old colleagues of mine at Ofwat about the arrangements they had, for example, for the Thames tideway tunnel. There, both the rhythm—by which I mean the frequency of reporting, monitoring and scrutiny of costs during construction—and the importance of having a dependable, expert, independent technical assurer on the costs are really important for making sure you have that right level of visibility and scrutiny. I would question the nature of unchecked costs. I am not denying that cost pressures would arise, but that is the whole point of having arrangements like an independent technical assessor.
Q One of the things that has come through from other witnesses today is the need for pace on this project—the status quo is appalling for my residents but every bad for the economy and for various sectors. Matt, would you say that the need for us to pass some legislation, then have an equity competition and then appoint the funders is slowing down your work to make sure that the project continues and completes on time—and hopefully on budget and on spec as well? Matt Palmer: We are moving at pace. The Chancellor at the last autumn Budget—not this one—announced funding to get us to private finance, and we are well into that. We are moving at pace. There is a misunderstanding that we have not started. We have very definitely started: 2,000 people are on site, we have 14 sq km of land and there is a lot of mud at the moment, I am afraid. We are moving well and at pace. Our target is to get a tunnel boring machine, which will be the largest in the world at the time, in the ground in 2028, which will line up roughly with when we go to private finance. All of that is contingent on the fact that we need the legislation through to allow us to get the equity to move on thereafter.
Q42 Good afternoon, gentlemen. Thank you for appearing before us. Clearly, this is a Bill of two halves: there is the specific stuff on the lower Thames crossing, and then it is a pretty open-ended book for other projects going forward. Can I have your initial assessment of whether this is the right model to solve both the question of getting the lower Thames crossing built and issues relating to future trunk road projects that may be required or identified in the country? Will it actually deliver value for the motorist and haulage businesses using the scheme? Do we even know that it will deliver to certain metrics? No one can give us an answer yet on what the toll would be on the lower Thames crossing, for example. Ben Hopkinson: We have quite serious concerns about the regulated asset base model. This will certainly be the first time it is been used for roads. The main issue is that there are quite limited incentives for cost control within a regulated asset base. If you are the private contractor, you have significant incentives to increase the capital expenditure on the regulated asset base to make it as large as possible, because that means you get as large a return on your investment as possible. The organisation standing in the way of that is the Office of Rail and Road in this case, and it has never overseen a RAB before. It would not even be able to look at other organisations or regulators that have overseen a RAB for roads, because there are none internationally. We have a better model through concessions. France has built more miles of motorway this century than the UK has in total. It has done that with the private sector working through concessions. Under a concession, there are strong incentives for private contractors to keep their costs as low as possible, because it directly impacts their bottom line, which is completely the opposite for a RAB model.
Q Good afternoon, gentlemen. Mr Hopkinson, you have expressed concerns about the limited incentives for cost control—presumably that is mainly in the construction part of the scheme; obviously, we are talking about the lower Thames crossing here. The Bill gives the ORR the ability to set licence conditions on economic allowances and expenditure controls, and provides for the investors to make a reasonable return. Those safeguards are set out. Do you not consider those sufficient and would you like to see something in addition? Ben Hopkinson: I am well aware that there are safeguards and that the regulator is tasked with ensuring that there are not runaway costs. However, the ORR has never done this before. No regulator has ever done a RAB for a road before. There is a real risk that if it sets the return too high, motorists will pay significantly more, but if it sets the return too low, then no one will want to invest. While in theory the model makes a lot of sense, I am a little worried about the practicalities of the ORR accidentally setting a rate too high or too low. In other sectors where rates are set by regulators, there are often risks, especially when there are macroeconomic shifts—higher interest rates, for example. Regulators are sometimes slow to update to that. There are concerns there. With a concession model, as used in France and around the world, there are much better incentives for contractors to keep costs down because they are the ones bearing them, not the potential motorists.